Standard Costing and Variance Analysis Formulas:

Learning Objective of the article:

  1. Learn the formulas to calculate direct materials, direct labor and factory overhead variances.

This is a collection of variance formulas / equations which can help you calculate variances for direct materials, direct labor, and factory overhead.

  1. Direct materials variances formulas
  2. Direct labor variances formulas
  3. Factory overhead variances formulas

Direct Materials Variances:

Materials purchase price variance Formula:
Materials purchase price variance = (Actual quantity purchased × Actual price) – (Actual quantity purchased × Standard price)

Materials price usage variance formula
Materials price usage variance = (Actual quantity used × Actual price) – (Actual quantity used × Standard price)

materials quantity / usage variance formula
Materials price usage variance = (Actual quantity used × Standard price) – (Standard quantity allowed × Standard price)

Materials mix variance formula
(Actual quantities at individual standard materials costs) –  (Actual quantities at weighted average of standard materials costs)

Materials yield variance formula
(Actual quantities at weighted average of standard materials costs) –  (Actual output quantity at standard materials cost)

Direct Labor Variances:

Direct labor rate / price variance formula:
(Actual hours worked × Actual rate) – (Actual hours worked × Standard rate)

Direct labor efficiency / usage / quantity formula:
(Actual hours worked × Standard rate) – (Standard hours allowed × Standard rate)

Direct labor yield variance formula:
(Standard hours allowed for expected output × Standard labor rate) – (Standard hours allowed for actual output × Standard labor rate)

Factory Overhead Variances:

Factory overhead controllable variance formula:
(
Actual factory overhead) – (Budgeted allowance based on standard hours allowed
*)

Factory overhead volume variance:
(Budgeted allowance based on standard hours allowed*) – (Factory overhead applied or charged to production**)

Factory overhead spending variance:
(Actual factory overhead) – (Budgeted allowance based on actual hours worked***)

Factory overhead idle capacity variance formula:
(Budgeted allowance based on actual hours worked***) – (Actual hours worked × Standard overhead rate)

Factory overhead efficiency variance formula:
(Actual hours worked × Standard overhead rate) – (Standard hours allowed for expected output × Standard overhead rate)

Variable overhead efficiency variance formula:
(Actual hours worked × Standard variable overhead rate) – (Standard hours allowed × Standard variable overhead rate)

Variable overhead efficiency variance formula:
(Actual hours worked × Fixed overhead rate) – (Standard hours allowed × Fixed overhead rate)

Factory overhead yield variance formula:
(Standard hours allowed for expected output × Standard overhead rate) – (Standard hours allowed for actual output × Standard overhead rate)


*Fixed overhead budgeted + Standard hours allowed × Standard variable overhead rate

**Standard hours allowed for actual production × Standard overhead rate

***Fixed overhead budgeted + Actual hours worked × Standard variable overhead rate

 

You may also be interested in other relevant articles:

 

Our Request

Dear visitor! Do you like this article? If you like, then please bookmark this page and also share with your friends. Thank you for your support.

 [Report Errors and Omissions]

 

Back to Home Page | Back to Standard Costing and Variance Analysis Main Page


Bookmark and Share
 


Our Message

We love our visitors and want to work for them.


Our Request

Knowledge is free for all. Please tell others about this site. Share this site at yahoo, Facebook, Google and other social sits and forums.
In this way you will encourage
accountingformanagement.com to continue writing high quality accounting articles for you.  Thank you for your support.


Managerial Accounting Articles
 
Business and Quality Improvement Programs
Cost Terms, Concepts and Classification
Job Order Costing system
Process Costing System
Process Costing System - Addition of Materials and Beginning Inventory
Controlling and Costing Materials
Materials and Inventory Cost Control
By Products and Joint Products Costing
Cost-Volume-Profit-Relationship
Variable Costing System
Activity Based Costing System
Budgeting and Planning
Standard Costing and Variance Analysis
Gross Profit Analysis
Linear Programming Technique
Segment Reporting and Transfer Pricing
Capital Budgeting Decisions
Service Department Costing
Preparing Cash Flow statement
Financial statement Analysis
Pricing Products and Services
Managerial Accounting Terms and Definitions
Managerial / Cost Accounting Formulas

Financial Accounting Articles
Bookkeeping and Bookkeeping Terms
Accounting Principles and Accounting Equation
Journal
Ledger
Accounting For Bills of Exchange
Subdivision of Journal
Final Accounts
Capital and Revenue Items
Single Entry System/Accounting From Incomplete Records
Accounting For Non-Trading Concerns
Accounting for Consignment / Consignment Accounts
Accounting for Joint Ventures
Accounting for Depreciation

Articles By International Authors

Accounting Articles

Advertisements

 
 

 
Home | Advertise With Us | Privacy Policy | Disclaimer & Terms of Use | Site map | Links | Link to us About Us | Contact Us

No text of this website can be republished without permission of the owner of this site and the authors of these managerial, management, and cost accounting articles. Otherwise sever civil and criminal penalties shall be imposed. All rights reserved.
Copy right © 2009