|
- |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Knowledge is free for all. Please tell others about this site | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Navigation: Standard Costing and Variance Analysis Case Study:
Case A:Effect of Assumed Standard Levels:Harden Company has experienced increased production costs. The primary area of concern identified by management is direct labor. The company is considering adopting a standard cost system to help control labor and other costs. Useful historical data are not available because detailed production records have not been maintained. To establish labor standards, Harden Company has retained an engineering consulting firm. After a complete study of the work process, the consultants recommended a labor standard of one unit of production every 30 minutes, or 16 units per day for each worker. The consultants further advised that Harden's wage rates were below the prevailing rate of $ per hour. Harden's production vice-president thought that this labor standard was too tight, and from experience with the labor force, believed that a labor standard of 40 minutes per unit or 12 units per day for each worker would be more reasonable. The president of Harden Company believed the standard should be set at a high level to motivate the workers and to provide adequate information for control and reasonable cost comparison. After much discussion, management decided to use a dual standard. The labor standard of one unit every 30 minutes, recommended by the consulting firm, would be employed in the plant as a motivation device, while a cost standard of 40 minutes per unit would be used in reporting. Management also concluded that the workers would not be informed of the cost standard used for reporting purposes. The production vice-president conducted several sessions prior to implementation in the plant, informing the workers of the new standard cost system and answering questions. The new standards were not related to incentive pay but were introduced when wages were increased to $7 per hour. The standard cost system was implemented on January 1, 19--. At the end of six months of operation, these statistics on labor performance were presented to executive management:
*U = Unfavorable; F = Favorable Materials quality, labor mix, and plant facilities and conditions have not changed to any great extent during the six month period. Required:
Answer:
Case B:Factory Overhead Variance Analysis:Strayer Company uses a standard cost system and budgets the following sales and costs for 19--
The 19-- budgeted sales level was the normal capacity level used in calculating the factory overhead predetermined standard cost rate per direct labor hour. At the end of 19--, Strayer Company reported production and sales of 19,200 units. Total factory overhead incurred was exactly equal to budgeted factory overhead for the year and there was under-applied total factory overhead of $2,000 at December 31. Factory overhead is applied to the work in process inventory on the basis of standard direct labor hours allowed for units produced. Although there was a favorable labor efficiency variance, there was neither a labor rate variance nor materials variances for the year. Require: An explanation of the under-applied factory overhead of $2,000, being as specific as the data permit and indicating the overhead variances affected. Strayer uses a three variance method to analyze the total factory overhead. Answer:Under-applied factory overhead will arise when actual factory overhead incurred is larger than the standard amount of factory overhead applied to work in process. The standard amount of factory overhead applied to work in process is based on actual rather than on budgeted units of output. Based on the information given, the sum of the factory overhead spending, efficiency, and idle capacity variances resulted in an unfavorable total factory overhead variance of $2,000. The factory overhead efficiency variance must be favorable because it is computed on the same basis as the direct labor efficiency variance which was given as favorable. Strayer would have an unfavorable idle capacity variance because the actual activity level for the year was less than the capacity level used in calculating the standard cost rate for factory overhead. As to the factory overhead spending variance, the balance would be unfavorable because actual costs would have had to exceed the budgeted cost of the actual units produced since the budget allowance for production of 19,200 units must be less than for 20,000 units and the actual costs were exactly equal to the budget allowance for 20,000 units. The magnitude of the spending variance is indeterminate from the information given. You may also be interested in other relevant articles:
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
No text of this website can
be republished without permission of the owner of this site and the authors
of these managerial, management, and cost accounting articles. Otherwise
sever civil and criminal penalties shall be imposed. All rights reserved. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||